GAO: Improvements in NASA Cost & Schedule Performance Might Not Be Sustainable

The LEMNOS project will provide laser communications services to NASA’s Orion vehicle, show in this artist concept. (Credit: NASA)

A new report from the Government Accountability Office (GAO) shows that NASA while has continued to improve its cost and schedule performance on major projects, the space agency might not be able to sustain the trend much longer due to projects such as the Space Launch System and Orion.

“The current trend is driven by two main factors: (1) most projects are being executed within their cost and schedule baselines; and (2) new projects, which are less likely to have experienced cost and schedule growth, were added to the portfolio,” the report stated.

“However, two projects—a Mars seismology instrument and lander and an upgrade to the NASA’s space communications network—experienced significant cost or schedule growth in 2016,” the assessment added. “In addition, eight projects are in the phase of development when cost and schedule problems are most likely to occur, including the Orion Multi-Purpose Crew Vehicle and Space Launch System, NASA’s most expensive human spaceflight programs.”

The conclusions are included in GAO’s annual assessment of NASA’s top 21 projects, which were defined as having life-cycle costs above $500 million.

The report’s executive summary is reproduced below.

NASA: Assessments of Major Projects
Report to Congressional Committees
Government Accountability Office
May 2017

[Full Report]

What GAO Found

The cost and schedule performance of the National Aeronautics and Space Administration’s (NASA) portfolio of major projects continued to improve, as shown in the figure below, but this trend may be difficult to sustain. The current trend is driven by two main factors: (1) most projects are being executed within their cost and schedule baselines; and (2) new projects, which are less likely to have experienced cost and schedule growth, were added to the portfolio. However, two projects—a Mars seismology instrument and lander and an upgrade to the NASA’s space communications network—experienced significant cost or schedule growth in 2016. In addition, eight projects are in the phase of development when cost and schedule problems are most likely to occur, including the Orion Multi-Purpose Crew Vehicle and Space Launch System, NASA’s most expensive human spaceflight programs.

Credit: GAO

NASA has generally maintained recent improvements in the technology maturity and design stability of its projects, even as the number of new technologies in its most recent projects has increased. Three of the four major projects that passed preliminary design review in the past year matured all technologies to the level recommended by GAO best practices. Several NASA projects experienced late design changes, but the overall level of these changes remained relatively low and other design stability measures remained unchanged.

NASA continues to improve project management tools to manage acquisition risks but faces workforce and funding challenges. NASA has not implemented a best practice for monitoring contractor performance, as GAO recommended in November 2012, due to resource constraints. Other NASA workforce analyses have identified gaps in key areas, such as scheduling. NASA dissolved its independent assessment office in October 2015, in part to bolster its mission directorate and center workforces. GAO is monitoring the effect this change could have on project oversight. Finally, several major projects experienced funding-related challenges, such as working to schedules that were not supported by NASA’s budget plans, which could affect cost and schedule
performance.

What GAO Recommends

In prior reports, GAO has made related recommendations that NASA generally agreed with, but has not yet fully addressed. GAO continues to believe they should be fully addressed. NASA generally agreed with GAO’s findings.

Why GAO Did This Study

This report provides GAO’s annual snapshot for 2017 of how well NASA is planning and executing its major acquisition projects. In March 2016, GAO found that projects continued a general positive trend of limiting cost and schedule growth, maturing technologies, and stabilizing designs, but that NASA faced several challenges that could affect its ability to effectively manage its portfolio. The explanatory statement of the House Committee on Appropriations accompanying the Omnibus
Appropriations Act, 2009 included a provision for GAO to prepare status reports on selected large-scale NASA programs, projects, and activities. This is GAO’s ninth annual assessment.

This report describes (1) the cost and schedule performance of NASA’s portfolio of major projects, (2) the maturity of technologies and stability of project designs at key milestones, and (3) NASA’s progress in implementing initiatives to manage acquisition risk and potential challenges for project management and oversight. This report also includes assessments of NASA’s 21 major projects, each with a life-cycle cost of over $250 million. To conduct its review, GAO analyzed cost, schedule, technology maturity, design stability, and other data; reviewed monthly project status reports; and interviewed NASA officials.