SpaceX Commercial Crew Milestones Update Report

SpaceX's Dragon spacecraft. (Credit: NASA)
SpaceX’s Dragon spacecraft. (Credit: NASA)

SpaceX CCiCAP Milestone Status Report
Award Period: August 2012 – August 2014
Milestones: 15
Milestones Completed: 10
Total: $310 Million out of $460 Million

As of Jan. 2, 2014, SpaceX has completed 10 of its 15 planned commercial milestones for a total of $310 million in payments out of a total of $460 million. The company completed Dragon parachute tests at the end of 2013. It is now awaiting NASA review and approval of that milestone, which is worth $20 million.

Major milestones for the coming year include pad abort and in-flight abort tests. The company also plans to complete an integrated critical design review later this year. NASA has extended the CCiCAP portion of commercial crew program to August.

SpaceX CCiCap Milestones

No.
DescriptionOriginal Date
StatusAmount
1CCiCap Kickoff Meeting. SpaceX will hold a kickoff meeting at the SpaceX headquarters in Hawthorne, CA, or a nearby facility to review the current state of existing hardware, processes and designs, describe plans for CCiCap program execution during both the base period and the optional period and lay the groundwork for a successful partnership between NASA and SpaceX.August 2012Complete$40
Million
2Financial and Business Review. SpaceX will hold a financial and business review to accomplish verification of financial ability to meet NASA’s stated goals for the CCiCap program by providing NASA insight into SpaceX finances.August 2012
Complete$20 Million
3Integrated System Requirements Review (ISRR). SpaceX will hold an integrated System Requirements Review (ISRR) to examine the functional and performance requirements defined for the entire CTS for the Commercial Crew Program design reference mission per section 3.1 of CCT-DRM-1110, as well as to evaluate the interpretation and applicability of each requirement.October 2012Complete$50 Million
4Ground Systems and Ascent Preliminary Design Review (PDR). SpaceX will hold a Ground Systems and Ascent Preliminary Design Review (PDR) to demonstrate that the overall CTS preliminary design for ground systems and ascent meets all requirements with acceptable risk and within schedule constraints and that it establishes the basis for proceeding with detailed design.December 2012Complete$35 Million
5Pad Abort Test Review. SpaceX will hold a Pad Abort Test Review to demonstrate the maturity of the pad abort test article design and test concept of operations.March 2013Complete$20 Million
6Human Certification Plan Review. SpaceX will hold a Human Certification Plan Review to present the Human Certification Plan. This Human Certification Plan Review will cover plans for certification of the design of the spacecraft, launch vehicle, and ground and mission operations systems.May 2013Complete$50 Million
7On-Orbit and Entry Preliminary Design Review (PDR). SpaceX will hold an On-Orbit and Entry Preliminary Design Review (PDR) to demonstrate that the overall CTS preliminary design for orbit, rendezvous and docking with the ISS, and entry flight regimes meets all requirements with acceptable risk and within schedule constraints and that it establishes the basis for proceeding with detailed design.July 2013Complete$35 Million
8In-Flight Abort Test Review. SpaceX will hold an In-Flight Abort Test Review to demonstrate the maturity of the in-flight abort test article design and test concept of operations.September 2013Complete$10 Million
9Safety Review. SpaceX will hold a Safety Review at the SpaceX headquarters in Hawthorne, CA, or a nearby facility to demonstrate that the CTS design is progressing toward meeting the Commercial Crew Program’s safety goals.October 2013Complete$50 Million
10Flight Review of Upgraded Falcon 9. SpaceX will conduct a review of a launch of the upgraded Falcon 9 launch vehicle demonstrating the operation of enhanced first-stage M1D engines, stage separation systems, enhanced second-stage MVacD engine and mission-critical vehicle telemetry during flight. Demonstration of the upgraded launch vehicle will serve as a risk reduction for the planned inflight abort test.November 2013Compete$0
TOTAL TO DATE
(OUT OF $460 MILLION):
$310 Million
15A&BDragon Parachute Tests. SpaceX will conduct parachute drop tests in order to validate the new parachute design as capable of supporting a pad abort event. Milestone 15A included a crane drop test. Milestone 15B featured a helicopter drop test.November 2013Tests Complete NASA Acceptance
Pending
$20 Million
11Pad Abort Test. SpaceX will conduct a pad abort test of the Dragon spacecraft. The scenario where an abort is initiated while the CTS is still on the pad is a design driver for the launch abort system as it dictates the total impulse and also requires parachute deployment in close proximity to the ground.December 2013Pending$30 Million
12Dragon Primary Structure Qualification. SpaceX will conduct static structural testing of all Dragon primary structure components to ultimate load factors, as applicable. This series of tests will validate the Dragon structure’s ability to maintain integrity during all driving load cases as well as verify the accuracy of math models used to analyze the Dragon structure. Individual tests will be designed to exercise all credible failure modes and minimum margin areas.January 2014Pending$30 Million
13Integrated Critical Design Review (CDR). SpaceX will hold an Integrated Critical Design Review (CDR) to demonstrate that the maturity of the CTS design is appropriate to support proceeding with full-scale fabrication, assembly, integration and test.March 2014Pending$40 Million
14In-Flight Abort Test. SpaceX will conduct an in-flight abort test of the Dragon spacecraft. The in-flight abort test will supplement the pad abort test and complete the corners-of-the-box stress cases. The in-flight abort scenario represents a Dragon abort while under propulsive flight of the launch vehicle during the worst-case dynamic loads on the CTS.April 2014Pending$30 Million
TOTAL:$460 Million