HAWTHORNE, Calif. (NASA PR) — Space Exploration Technologies Corp. (SpaceX) of Hawthorne, Calif., recently completed two milestones for NASA’s Commercial Crew Integrated Capability (CCiCap) initiative, which is intended to make commercial human spaceflight services available for government and commercial customers.

These were the fifth and sixth milestones for SpaceX, a partner in NASA’s Commercial Crew Program (CCP). The company is on track to complete all 14 of its CCiCap milestones by mid-2014.

In a human certification plan review May 7, SpaceX outlined all the steps the company plans to take to certify its system for crewed missions, including testing, demonstrations, analyses, inspections, verifications and training events. This was a key milestone to ensure SpaceX’s integrated Falcon 9 rocket and Dragon capsule will be safe to carry humans to and from low-Earth orbit beginning in the middle of this decade.

At its pad abort test review, SpaceX presented plans for a pad abort test, currently targeted for later this year or early next year from Cape Canaveral Air Force Station’s Space Launch Complex 40 in Florida. The review successfully demonstrated the adequacy of the test plan objectives and the pad abort scenario.

“The beauty of having the pad abort test review was it allowed both NASA and SpaceX to start coalescing toward an understanding of what will be tested and how we’ll measure success,” said Ed Mango, NASA’s CCP manager. “We’re really looking forward to seeing SpaceX’s pad abort system take off from along Florida’s Space Coast.”

During the upcoming pad abort test, SpaceX will perform a recovery operation following a simulated Falcon 9 anomaly. Plans call for the company to put one of its Dragon capsules on a launch pad test stand, countdown to T-0, ignite the system’s SuperDraco abort engines and initiate a separation command. At around 5,000 feet, the spacecraft’s parachutes will deploy resulting in a splashdown in the Atlantic Ocean.

SpaceX is one of three U.S. companies participating in NASA’s CCiCap initiative. Future development and certification initiatives eventually will lead to the availability of human spaceflight services for NASA to send its astronauts to the International Space Station.

For more information about NASA’s Commercial Crew Program and its aerospace industry partners, visit: http://www.nasa.gov/commercialcrew

SpaceX CCiCAP Milestone Status
Award Period: August 2012 – April 2014
Total: $440 Million

No.
DescriptionDateStatusAmount
1.CCiCap Kickoff Meeting. SpaceX will hold a kickoff meeting at the SpaceX headquarters in Hawthorne, CA, or a nearby facility to review the current state of existing hardware, processes and designs, describe plans for CCiCap program execution during both the base period and the optional period and lay the groundwork for a successful partnership between NASA and SpaceX.August 2012Complete$60
Million
2.Financial and Business Review. SpaceX will hold a financial and business review to accomplish verification of financial ability to meet NASA’s stated goals for the CCiCap program by providing NASA insight into SpaceX finances.August 2012
Complete$20 Million
3.Integrated System Requirements Review (ISRR). SpaceX will hold an integrated System Requirements Review (ISRR) to examine the functional and performance requirements defined for the entire CTS for the Commercial Crew Program design reference mission per section 3.1 of CCT-DRM-1110, as well as to evaluate the interpretation and applicability of each requirement.October 2012Complete$50 Million
4.Ground Systems and Ascent Preliminary Design Review (PDR). SpaceX will hold a Ground Systems and Ascent Preliminary Design Review (PDR) to demonstrate that the overall CTS preliminary design for ground systems and ascent meets all requirements with acceptable risk and within schedule constraints and that it establishes the basis for proceeding with detailed design.December 2012Complete$35 Million
5.Pad Abort Test Review. SpaceX will hold a Pad Abort Test Review to demonstrate the maturity of the pad abort test article design and test concept of operations.March 2013Complete$20 Million
6.Human Certification Plan Review. SpaceX will hold a Human Certification Plan Review to present the Human Certification Plan. This Human Certification Plan Review will cover plans for certification of the design of the spacecraft, launch vehicle, and ground and mission operations systems.May 2013Pending$50 Million
TOTAL TO DATE
(OUT OF $440 MILLION):
$235 Million
7.On-Orbit and Entry Preliminary Design Review (PDR). SpaceX will hold an On-Orbit and Entry Preliminary Design Review (PDR) to demonstrate that the overall CTS preliminary design for orbit, rendezvous and docking with the ISS, and entry flight regimes meets all requirements with acceptable risk and within schedule constraints and that it establishes the basis for proceeding with detailed design.July 2013Pending$35 Million
8.In-Flight Abort Test Review. SpaceX will hold an In-Flight Abort Test Review to demonstrate the maturity of the in-flight abort test article design and test concept of operations.September 2013Pending$10 Million
9.Safety Review. SpaceX will hold a Safety Review at the SpaceX headquarters in Hawthorne, CA, or a nearby facility to demonstrate that the CTS design is progressing toward meeting the Commercial Crew Program’s safety goals.October 2013Pending$50 Million
10.Flight Review of Upgraded Falcon 9. SpaceX will conduct a review of a launch of the upgraded Falcon 9 launch vehicle demonstrating the operation of enhanced first-stage M1D engines, stage separation systems, enhanced second-stage MVacD engine and mission-critical vehicle telemetry during flight. Demonstration of the upgraded launch vehicle will serve as a risk reduction for the planned inflight abort test.November 2013Pending$0
11.Pad Abort Test. SpaceX will conduct a pad abort test of the Dragon spacecraft. The scenario where an abort is initiated while the CTS is still on the pad is a design driver for the launch abort system as it dictates the total impulse and also requires parachute deployment in close proximity to the ground.December 2013Pending$30 Million
12.Dragon Primary Structure Qualification. SpaceX will conduct static structural testing of all Dragon primary structure components to ultimate load factors, as applicable. This series of tests will validate the Dragon structure’s ability to maintain integrity during all driving load cases as well as verify the accuracy of math models used to analyze the Dragon structure. Individual tests will be designed to exercise all credible failure modes and minimum margin areas.January 2014Pending$30 Million
13.Integrated Critical Design Review (CDR). SpaceX will hold an Integrated Critical Design Review (CDR) to demonstrate that the maturity of the CTS design is appropriate to support proceeding with full-scale fabrication, assembly, integration and test.March 2014Pending$30 Million
14.In-Flight Abort Test. SpaceX will conduct an in-flight abort test of the Dragon spacecraft. The in-flight abort test will supplement the pad abort test and complete the corners-of-the-box stress cases. The in-flight abort scenario represents a Dragon abort while under propulsive flight of the launch vehicle during the worst-case dynamic loads on the CTS.April 2014Pending$30 Million
TOTAL:$440 Million