VLS-1 Launch Complex Readied at Alcantara

IAE PR — System Platform Release VLS-1 (SISPLAT) is nearing completion at the Alcantara Launch Center (CLA). The panels are already physically installed, the installed lighting, cameras installed Closed Circuit TV system, air conditioning and pressurization installed, Detection and Alarm Fire Fighting in the final stage, a protection system against lightning strikes in the final stage. According to the schedule of the Consortium JARAGUÁ / LAVITTA, will start next October to start tweaking and testing the installation of the automation system.

These activities will take place until late December or early January 2012. Concluded this phase is planned to integrate the mock-up (MIR), to receive the final piece in the months of March and April. This integration is only possible in March because it is the same mock-up that is in separation tests.