In the latest of a series of critical investigations, NASA’s Office of Inspector General released a report on Wednesday concerning the agency’s decision to build a new rocket test facility for its Ares program at the Stennis Space Center in Mississippi. An excerpt from the report follows:
“The NRPTA [National Rocket Propulsion Test Alliance], formed by an agreement between NASA and the Department of Defense (DoD), was established to shape the Government’s rocket propulsion testing capability to efficiently meet national test needs through intra- and inter-agency cooperation. The NRPTA reviews testing needs and recommends solutions that provide the best overall value to the taxpayer. NASA’s Rocket Propulsion Test Management Board (RPTMB) serves as the NASA decision-making body for rocket propulsion testing.
“We found that NASA’s Upper Stage Engine (USE) Element Manager, located at Marshall Space Flight Center in Alabama, reviewed the J-2X rocket propulsion testing options and selected the A-3 test stand to be built at Stennis without the required formal reviews or recommendations of the NRPTA, or NASA’s RPTMB. This occurred because NASA did not appropriately engage the NRPTA as required by the NRPTA Memorandum of Agreement (MOA). The NRPTA MOA and the RPTMB Operating Procedures require member reviews and recommendations prior to major test facility investments or modifications. In addition, we found that the processes contained in the the NRPTA MOA and the RPTMB Operating Procedures are not included in either a NASA Policy Directive or NASA Procedural Requirements.
“Although the Rocket Propulsion Test (RPT) Program office used the NRPTA to gather information on potential J-2X testing options, NASA did not make a request for NRPTA member reviews and recommendations and subsequently made a unilateral decision to build the A-3 test stand at Stennis. The USE Element Manager stated that he selected the A-3 without, or prior to, receiving any recommendations from the RPTMB or NRPTA because the selection needed to be made in March 2007 to maintain the critical path of the Ares Project. We confirmed that the test facility was on the Ares Project’s critical path. However, we found that the schedules projected for the A-3 and upgrading AEDC’s J-4 facility, which presented a competing option, were the same, 3½ years. Although the critical path of the Ares Project may explain the timing of the decision, it does not adequately justify the decision to build the A-3 exclusive of cost and technical risk comparisons with other facilities as would have been provided if the appropriate request was made of the NRPTA.”












0 Responses to “IG: NASA Ignored Agreement, Made Unilateral Decision on Stennis Rocket Test Facility”
Leave a Reply